#!/usr/bin/env python3
"""Plan an ISO 9001 certification timeline from start to certificate, plus the 3-year audit cycle.

Phase lengths scale with headcount and starting maturity; the records period before stage 2 is fixed at
12 weeks minimum because certification bodies want to see the system operating (one internal audit cycle and
one management review). Audit days follow the IAF MD 5 QMS table (initial = stage 1 + stage 2; surveillance
about 1/3 and recertification about 2/3 of initial); certification bodies adjust by up to +/-30% for
complexity, design responsibility and sites.

Usage:
    python roadmap.py --start 2026-11-02 --employees 40
    python roadmap.py --start 2026-11-02 --employees 180 --maturity partial --target 2027-06-30
    python roadmap.py --start 2026-11-02 --employees 12 --maturity basic --json

Maturity: none (no QMS), basic (some procedures/records exist), partial (another ISO system or a lapsed QMS).
Exit codes: 0 plan printed (target met if given), 1 target date not achievable, 2 usage error.
"""

import argparse
import datetime as dt
import json
import sys

# IAF MD 5 QMS table: (max effective personnel, initial audit days for stage 1 + stage 2)
MD5 = [(5, 1.5), (10, 2), (15, 2.5), (25, 3), (45, 4), (65, 5), (85, 6), (125, 7), (175, 8), (275, 9),
       (425, 10), (625, 11), (875, 12), (1175, 13), (1550, 14), (2025, 15), (2675, 16), (3450, 17),
       (4350, 18), (5450, 19), (6800, 20), (8500, 21), (10700, 22)]
MATURITY = {"none": 1.0, "basic": 0.75, "partial": 0.5}

# (phase, base weeks, scales with size/maturity, starts after phase index or None = previous, deliverable)
PHASES = [
    ("Gap analysis and project set-up", 3, True, "Gap report, project plan, steering group, budget"),
    ("Context, scope, processes, policy, objectives", 4, True, "Issue and party registers, scope, process map, policy, objectives"),
    ("Document and implement processes", 10, True, "Procedures, WIs, forms, registers in use; risk register"),
    ("Train staff and internal auditors", 3, True, "Awareness for all; 2+ trained internal auditors"),
    ("Operate the QMS and build records", 12, False, "At least 3 months of records for every process"),
    ("Full internal audit cycle", 4, True, "Audit of every process and clause; corrective actions raised"),
    ("Management review", 1, False, "Minutes covering all 9.3.2 inputs and decisions"),
    ("Stage 1 audit (readiness)", 1, False, "Stage 1 report: concerns to close before stage 2"),
    ("Close stage 1 concerns", 3, False, "Evidence for every stage 1 concern"),
    ("Stage 2 audit (certification)", 1, False, "Stage 2 report: recommendation or nonconformities"),
    ("Close nonconformities and certificate", 6, False, "Corrective action plans accepted; certificate issued"),
]


def audit_days(n):
    for cap, days in MD5:
        if n <= cap:
            return days
    return 22 + 0.5 * ((n - 10700) // 2000 + 1)  # approximate progression above the table


def size_factor(n):
    return 1.0 if n <= 25 else 1.25 if n <= 100 else 1.5 if n <= 500 else 2.0


def plan(start, n, maturity):
    f = size_factor(n) * MATURITY[maturity]
    rows, cur = [], start
    audit_start = None
    for i, (name, weeks, scales, deliverable) in enumerate(PHASES):
        w = max(1, round(weeks * f)) if scales else weeks
        if i == 3:      # training runs alongside implementation: starts 2 weeks before it ends
            s = rows[2][2] - dt.timedelta(weeks=min(2, rows[2][3]))
        elif i == 5:    # internal audit happens in the last part of the records period
            s = rows[4][2] - dt.timedelta(weeks=w + 1)
            audit_start = s
        elif i == 6:
            s = max(cur, audit_start + dt.timedelta(weeks=rows[5][3]))
        else:
            s = cur
        e = s + dt.timedelta(weeks=w)
        rows.append((name, s, e, w, deliverable))
        cur = max(cur, e) if i not in (3, 5) else cur
        if i == 3:
            cur = max(rows[2][2], e)
    return rows


def main():
    ap = argparse.ArgumentParser(description=__doc__, formatter_class=argparse.RawDescriptionHelpFormatter)
    ap.add_argument("--start", type=dt.date.fromisoformat, required=True, help="project start YYYY-MM-DD")
    ap.add_argument("--employees", type=int, required=True, help="effective number of personnel in scope")
    ap.add_argument("--maturity", choices=MATURITY, default="none")
    ap.add_argument("--target", type=dt.date.fromisoformat, help="desired certificate date")
    ap.add_argument("--json", action="store_true")
    a = ap.parse_args()
    if a.employees < 1:
        print("error: --employees must be at least 1", file=sys.stderr)
        return 2
    rows = plan(a.start, a.employees, a.maturity)
    cert = rows[-1][2]
    days = audit_days(a.employees)
    # surveillance within 12 months of the certification decision, then yearly; recertification before expiry
    cycle = [("Surveillance audit 1", cert + dt.timedelta(days=365), round(days / 3, 1)),
             ("Surveillance audit 2", cert + dt.timedelta(days=730), round(days / 3, 1)),
             ("Recertification audit", cert + dt.timedelta(days=1095 - 90), round(days * 2 / 3, 1))]
    ok = a.target is None or cert <= a.target
    if a.json:
        print(json.dumps({"phases": [{"phase": r[0], "start": str(r[1]), "end": str(r[2]), "weeks": r[3],
                                      "deliverable": r[4]} for r in rows],
                          "initial_audit_days": days, "certificate": str(cert),
                          "cycle": [{"audit": c[0], "by": str(c[1]), "days": c[2]} for c in cycle],
                          "target_met": ok}, indent=2))
    else:
        print(f"ISO 9001 roadmap: {a.employees} people, maturity '{a.maturity}', start {a.start}\n")
        print(f"{'Phase':<48}{'Start':<12}{'End':<12}{'Wks':>4}  Deliverable")
        for name, s, e, w, d in rows:
            print(f"{name:<48}{s!s:<12}{e!s:<12}{w:>4}  {d}")
        months = (cert - a.start).days / 30.4
        print(f"\nCertificate expected: {cert} (~{months:.0f} months)")
        print(f"Audit days (IAF MD 5, before CB adjustments): initial {days:g} (stage 1 + stage 2)")
        for name, by, d in cycle:
            print(f"  {name:<24} by {by}  ~{d:g} days")
        print("Book the certification body by "
              f"{rows[7][1] - dt.timedelta(weeks=8)} (8 weeks' lead time before stage 1).")
        if a.target:
            gap = (a.target - cert).days
            print(f"Target {a.target}: " + (f"achievable with {gap} days' slack" if ok else
                  f"NOT achievable - {-gap} days short; raise maturity (consultant, existing system) or move the date"))
    return 0 if ok else 1


if __name__ == "__main__":
    sys.exit(main())
More in Quality Management & ISO 9001

8d-problem-solving-report-writer

Write and review 8D problem-solving reports for customer complaints and serious nonconformities (automotive and aerospace practice: Ford Global 8D, VDA, GM, Stellantis formats): D0 emergency response, D1 cross-functional team and champion, D2 problem description with 5W2H and is / is-not and no cause in the statement, D3 interim containment within 24 hours with verification and clean point, D4 verified occurrence and escape (non-detection) root causes plus systemic cause, D5 permanent corrective actions for each cause verified before implementation, D6 implementation, validation with production data and removal of containment, D7 PFMEA, control plan and read-across to similar products, D8 closure and recognition. Checks an 8D discipline by discipline for missing content, human-error root causes, missing escape cause or action, late containment and dates out of order.

acceptance-sampling-plan-selector

Select and evaluate acceptance sampling plans for incoming, in-process and final inspection: ANSI/ASQ Z1.4 / ISO 2859-1 single sampling under normal inspection (code letter from lot size and inspection level I, II, III, S-1 to S-4; sample size, Ac and Re from AQL, following the table's arrows to the correct plan; 100% when n reaches the lot size; AQLs above 10 per 100 units), operating characteristic curves (Pa at any quality, producer's quality level, indifference point, LTPD, AOQ and AOQL, binomial or hypergeometric), plans designed from producer and consumer risk, and c = 0 zero-acceptance plans. Covers AQL choice by defect class, switching rules between normal, tightened and reduced inspection, when sampling is not appropriate, and random sampling.

approved-supplier-list-manager

Manage and audit an approved supplier list (ASL) / external provider register for ISO 9001 8.4.1, IATF 16949 8.4 and AS9100 8.4.1: supplier status (approved, conditional, probation, pending, disqualified), scope of approval by commodity and process, risk class, certification and expiry, re-evaluation intervals by risk, conditions with end dates, single-source contingency, approver and customer-directed sources. Audits the list for expired or expiring certificates, overdue re-evaluations, conditional or probation status past its decision date, high-risk suppliers without the required certification, single-source suppliers without backup and missing approvers, and checks purchase orders for suppliers that are off-list, disqualified or pending, or buying outside the approved scope. Covers ERP blocks, PO requirements, off-list and emergency purchases.

apqp-phase-planner

Plan and track Advanced Product Quality Planning (AIAG APQP 3rd edition, IATF 16949) for a new or changed automotive part: back-schedule the five phases (plan and define, product design, process design, product and process validation, launch and feedback) from the start-of-production date by program complexity, with overlap, PPAP lead and safe-launch period; list the deliverables and gate for each phase (DFMEA, DVP&R, feasibility, process flow, PFMEA, control plans, MSA, Ppk, run at rate, PPAP, safe launch, lessons learned); adjust for build-to-print suppliers; flag compressed timelines and late or untracked deliverables against a status list. Covers gate reviews, red/yellow/green status reporting, run at rate and safe-launch exit criteria.

as9100-gap-analyzer

Run an AS9100D / EN 9100:2018 gap analysis for aviation, space and defence suppliers on the requirements added to ISO 9001: on-time delivery and conformity focus, management representative, ethics and human-factors awareness, operational planning and operational risk management, configuration management, product safety, counterfeit-part prevention, special requirements, critical items and key characteristics, external provider register and flow-down, FOD prevention, tooling and NC program control, special process validation, first article inspection (AS9102), traceability, in-service data and nonconforming product control. Generates and scores a worksheet, grades missing core controls as major, and checks invalid n/a claims. Covers AS9101/AS9104, OASIS, AS9102 FAI forms, counterfeit standards (AS5553, AS6174, AS6081), NADCAP and the planned IA9100 transition.

audit-report-writer

Write internal, supplier and pre-certification audit reports with the content ISO 19011:2018 6.5 expects: audit objectives, scope, criteria with revisions, dates, team and auditees, method and sampling statement, specific strengths, findings table and three-part finding details (requirement, evidence, statement), conclusion on the degree of fulfilment of criteria, diverging opinions, follow-up deadlines and distribution. Builds a Markdown report from a JSON audit record, generates the conclusion from the findings (major / minor / none) and flags reports missing required content or findings without clause or evidence. Covers conclusion wording, closing meetings, response expectations and verifying corrective actions.