Audit Time and Project Planning

Reference for iso-9001-certification-roadmap-planner · 55 lines

IAF MD 5 audit days (QMS, initial = stage 1 + stage 2)

Effective personnelDaysEffective personnelDays
1-51.5426-62511
6-102626-87512
11-152.5876-117513
16-2531176-155014
26-4541551-202515
46-6552026-267516
66-8562676-345017
86-12573451-435018
126-17584351-545019
176-27595451-680020
276-425106801-850021
8501-1070022

Surveillance is about one third and recertification about two thirds of the initial time. CBs adjust for complexity: up for design responsibility, many processes, multiple shifts or high risk; down for low-risk processes, repetitive work or a mature integrated system (reductions usually capped at 30%). Part-time staff and repetitive work can reduce the effective personnel count. Multi-site organizations may qualify for site sampling (IAF MD 1). Verify the current MD 5 edition with the CB.

Typical durations

OrganizationFrom scratch to certificate
< 25 people, simple processes6-9 months
25-100 people9-12 months
100-500 people, several sites12-18 months
Existing ISO 14001/45001 or customer-approved system4-8 months

roadmap.py models this: build phases scale with headcount (x1 up to 25, x1.25 to 100, x1.5 to 500, x2 above) and maturity (none x1, basic x0.75, partial x0.5); the 12-week records period and audit stages do not scale.

Project governance

ElementRecommendation
SponsorManaging director (5.1 needs top-management ownership)
Project leadQuality manager or trained coordinator, 30-60% of time for a 50-person company
Steering meetingEvery 2 weeks: progress vs roadmap, blocked items, decisions
Process ownersWrite and run their own processes; QM coaches
BudgetTraining, CB fees (3-year cycle), possible consultant, software (eQMS), staff time
Milestones to reportGap report, process map approved, documents released, first audit cycle complete, MR held, stage 1, stage 2

Risks to the timeline

  • Process owners not released from daily work -> documents late.
  • Internal auditors not trained in time -> audit cycle slips -> stage 1 slips.
  • CB booked late -> 6-10 week wait.
  • Design responsibility discovered late -> 8.3 must be implemented and the scope changed.
More in Quality Management & ISO 9001

8d-problem-solving-report-writer

Write and review 8D problem-solving reports for customer complaints and serious nonconformities (automotive and aerospace practice: Ford Global 8D, VDA, GM, Stellantis formats): D0 emergency response, D1 cross-functional team and champion, D2 problem description with 5W2H and is / is-not and no cause in the statement, D3 interim containment within 24 hours with verification and clean point, D4 verified occurrence and escape (non-detection) root causes plus systemic cause, D5 permanent corrective actions for each cause verified before implementation, D6 implementation, validation with production data and removal of containment, D7 PFMEA, control plan and read-across to similar products, D8 closure and recognition. Checks an 8D discipline by discipline for missing content, human-error root causes, missing escape cause or action, late containment and dates out of order.

acceptance-sampling-plan-selector

Select and evaluate acceptance sampling plans for incoming, in-process and final inspection: ANSI/ASQ Z1.4 / ISO 2859-1 single sampling under normal inspection (code letter from lot size and inspection level I, II, III, S-1 to S-4; sample size, Ac and Re from AQL, following the table's arrows to the correct plan; 100% when n reaches the lot size; AQLs above 10 per 100 units), operating characteristic curves (Pa at any quality, producer's quality level, indifference point, LTPD, AOQ and AOQL, binomial or hypergeometric), plans designed from producer and consumer risk, and c = 0 zero-acceptance plans. Covers AQL choice by defect class, switching rules between normal, tightened and reduced inspection, when sampling is not appropriate, and random sampling.

approved-supplier-list-manager

Manage and audit an approved supplier list (ASL) / external provider register for ISO 9001 8.4.1, IATF 16949 8.4 and AS9100 8.4.1: supplier status (approved, conditional, probation, pending, disqualified), scope of approval by commodity and process, risk class, certification and expiry, re-evaluation intervals by risk, conditions with end dates, single-source contingency, approver and customer-directed sources. Audits the list for expired or expiring certificates, overdue re-evaluations, conditional or probation status past its decision date, high-risk suppliers without the required certification, single-source suppliers without backup and missing approvers, and checks purchase orders for suppliers that are off-list, disqualified or pending, or buying outside the approved scope. Covers ERP blocks, PO requirements, off-list and emergency purchases.

apqp-phase-planner

Plan and track Advanced Product Quality Planning (AIAG APQP 3rd edition, IATF 16949) for a new or changed automotive part: back-schedule the five phases (plan and define, product design, process design, product and process validation, launch and feedback) from the start-of-production date by program complexity, with overlap, PPAP lead and safe-launch period; list the deliverables and gate for each phase (DFMEA, DVP&R, feasibility, process flow, PFMEA, control plans, MSA, Ppk, run at rate, PPAP, safe launch, lessons learned); adjust for build-to-print suppliers; flag compressed timelines and late or untracked deliverables against a status list. Covers gate reviews, red/yellow/green status reporting, run at rate and safe-launch exit criteria.

as9100-gap-analyzer

Run an AS9100D / EN 9100:2018 gap analysis for aviation, space and defence suppliers on the requirements added to ISO 9001: on-time delivery and conformity focus, management representative, ethics and human-factors awareness, operational planning and operational risk management, configuration management, product safety, counterfeit-part prevention, special requirements, critical items and key characteristics, external provider register and flow-down, FOD prevention, tooling and NC program control, special process validation, first article inspection (AS9102), traceability, in-service data and nonconforming product control. Generates and scores a worksheet, grades missing core controls as major, and checks invalid n/a claims. Covers AS9101/AS9104, OASIS, AS9102 FAI forms, counterfeit standards (AS5553, AS6174, AS6081), NADCAP and the planned IA9100 transition.

audit-report-writer

Write internal, supplier and pre-certification audit reports with the content ISO 19011:2018 6.5 expects: audit objectives, scope, criteria with revisions, dates, team and auditees, method and sampling statement, specific strengths, findings table and three-part finding details (requirement, evidence, statement), conclusion on the degree of fulfilment of criteria, diverging opinions, follow-up deadlines and distribution. Builds a Markdown report from a JSON audit record, generates the conclusion from the findings (major / minor / none) and flags reports missing required content or findings without clause or evidence. Covers conclusion wording, closing meetings, response expectations and verifying corrective actions.