Skip to content
v0.1.3latest release121 skills4 categories6 sub-categories247 tested scripts397 reference docsContact us

PSW, Acceptance Criteria and Approval Status

Reference for ppap-submission-package-builder · 44 lines

Manufacturing & Industrial Operations / Quality Management & ISO 9001v1.0.0Updated OCT 25 20262 references2 scripts

PSW content

SectionFields
Part informationPart number and name, drawing number and revision, engineering change level and date, safety / government regulation flag, PO number, weight (kg, 4 decimals), checking aid number and change level
OrganizationSupplier name, code, manufacturing site address
Material reportingIMDS or other customer format, submission ID; substances of concern declaration
Reason for submissionInitial, engineering change, tooling, correction of discrepancy, material/sub-supplier change, process change, inactive tooling, other
Submission level1-5
ResultsDimensional, material/functional, appearance, statistical process package: meets all requirements yes/no
DeclarationSamples representative of parts made with production tooling and processes at the quoted rate; signed by an authorized person with title, phone, date
Customer use onlyApproval disposition and signature

Never sign "meets all requirements" with a known nonconformity: submit with a documented deviation or interim approval request instead.

Initial process study acceptance (special characteristics)

Result (stable process)Interpretation
Index > 1.67Meets acceptance
1.33 <= index <= 1.67May be acceptable; contact the customer and review
Index < 1.33Does not meet acceptance; contact the customer; 100% inspection and a corrective action plan

Use Ppk for initial studies when data are from a short run; Cpk when the process is stable over time. At least 100 readings in 25 or more subgroups (or as the customer agrees). Unstable processes, one-sided specifications or non-normal data: agree the approach with the customer before submission.

Customer approval status

StatusMeaningSupplier action
ApprovedPart meets all requirementsShip production quantities
Interim approvalLimited time or quantity approvalShip within the limits; close the action plan; resubmit
RejectedDoes not meet requirementsCorrect and resubmit; no production shipments

Dimensional results

Ballooned drawing, every characteristic with specification, measured values per sample (commonly 5 parts per cavity, mould, die, line or process stream), OK/NOK, measuring equipment. Any NOK result blocks "meets all requirements" unless covered by an approved deviation.

More in Quality Management & ISO 9001

8d-problem-solving-report-writer

Write and review 8D problem-solving reports for customer complaints and serious nonconformities (automotive and aerospace practice: Ford Global 8D, VDA, GM, Stellantis formats): D0 emergency response, D1 cross-functional team and champion, D2 problem description with 5W2H and is / is-not and no cause in the statement, D3 interim containment within 24 hours with verification and clean point, D4 verified occurrence and escape (non-detection) root causes plus systemic cause, D5 permanent corrective actions for each cause verified before implementation, D6 implementation, validation with production data and removal of containment, D7 PFMEA, control plan and read-across to similar products, D8 closure and recognition. Checks an 8D discipline by discipline for missing content, human-error root causes, missing escape cause or action, late containment and dates out of order.

acceptance-sampling-plan-selector

Select and evaluate acceptance sampling plans for incoming, in-process and final inspection: ANSI/ASQ Z1.4 / ISO 2859-1 single sampling under normal inspection (code letter from lot size and inspection level I, II, III, S-1 to S-4; sample size, Ac and Re from AQL, following the table's arrows to the correct plan; 100% when n reaches the lot size; AQLs above 10 per 100 units), operating characteristic curves (Pa at any quality, producer's quality level, indifference point, LTPD, AOQ and AOQL, binomial or hypergeometric), plans designed from producer and consumer risk, and c = 0 zero-acceptance plans. Covers AQL choice by defect class, switching rules between normal, tightened and reduced inspection, when sampling is not appropriate, and random sampling.

approved-supplier-list-manager

Manage and audit an approved supplier list (ASL) / external provider register for ISO 9001 8.4.1, IATF 16949 8.4 and AS9100 8.4.1: supplier status (approved, conditional, probation, pending, disqualified), scope of approval by commodity and process, risk class, certification and expiry, re-evaluation intervals by risk, conditions with end dates, single-source contingency, approver and customer-directed sources. Audits the list for expired or expiring certificates, overdue re-evaluations, conditional or probation status past its decision date, high-risk suppliers without the required certification, single-source suppliers without backup and missing approvers, and checks purchase orders for suppliers that are off-list, disqualified or pending, or buying outside the approved scope. Covers ERP blocks, PO requirements, off-list and emergency purchases.

apqp-phase-planner

Plan and track Advanced Product Quality Planning (AIAG APQP 3rd edition, IATF 16949) for a new or changed automotive part: back-schedule the five phases (plan and define, product design, process design, product and process validation, launch and feedback) from the start-of-production date by program complexity, with overlap, PPAP lead and safe-launch period; list the deliverables and gate for each phase (DFMEA, DVP&R, feasibility, process flow, PFMEA, control plans, MSA, Ppk, run at rate, PPAP, safe launch, lessons learned); adjust for build-to-print suppliers; flag compressed timelines and late or untracked deliverables against a status list. Covers gate reviews, red/yellow/green status reporting, run at rate and safe-launch exit criteria.

as9100-gap-analyzer

Run an AS9100D / EN 9100:2018 gap analysis for aviation, space and defence suppliers on the requirements added to ISO 9001: on-time delivery and conformity focus, management representative, ethics and human-factors awareness, operational planning and operational risk management, configuration management, product safety, counterfeit-part prevention, special requirements, critical items and key characteristics, external provider register and flow-down, FOD prevention, tooling and NC program control, special process validation, first article inspection (AS9102), traceability, in-service data and nonconforming product control. Generates and scores a worksheet, grades missing core controls as major, and checks invalid n/a claims. Covers AS9101/AS9104, OASIS, AS9102 FAI forms, counterfeit standards (AS5553, AS6174, AS6081), NADCAP and the planned IA9100 transition.

audit-report-writer

Write internal, supplier and pre-certification audit reports with the content ISO 19011:2018 6.5 expects: audit objectives, scope, criteria with revisions, dates, team and auditees, method and sampling statement, specific strengths, findings table and three-part finding details (requirement, evidence, statement), conclusion on the degree of fulfilment of criteria, diverging opinions, follow-up deadlines and distribution. Builds a Markdown report from a JSON audit record, generates the conclusion from the findings (major / minor / none) and flags reports missing required content or findings without clause or evidence. Covers conclusion wording, closing meetings, response expectations and verifying corrective actions.