Register (master list) columns

ColumnWhy
doc_idUnique, stable ID; never reused
titleHuman-readable name
typeQM, QP, WI, QF, SP, DWG, EXT, REC
revisionLetter or number; separate from the ID
statusdraft / approved / obsolete
ownerRole responsible for content
approved_by, approval_dateEvidence of approval (7.5.2 c)
last_review, review_monthsDrives periodic review (typically 24 months for procedures, 12 for external standards)
retentionRequired for record series
locationsPoints of use for controlled copies, so withdrawal is complete
parentProcedure a form or WI belongs to

Run register_audit.py monthly and before every audit.

Numbering rules

  1. Type prefix + sequence (QP-007), optionally with an area code (WI-PRD-014) for large sites.
  2. Revision is not in the ID (QP-007 rev D, not QP-007D): links and references stay valid across revisions.
  3. Never reuse a retired number; retired IDs stay in the register as obsolete.
  4. Keep the ID when the title changes. Change history explains the rename.
  5. Forms point to their parent in the register, not through the ID (QF-031, parent QP-007): forms move between procedures more often than IDs can.
  6. Avoid meaning-laden numbers (8.7-01 tied to the ISO clause): the standard's numbering changes, yours should not.
  7. Size the sequence to the expected volume: 3 digits for small companies, 4 for multi-site.

Revision conventions

ConventionUse
Letters A, B, C ... for released, numbers 0.1, 0.2 for draftsCommon in manufacturing
Integers 1, 2, 3Simple; fine for eQMS that tracks drafts separately
Change summary in a revision table at the endRequired in practice: auditors ask "what changed?"

Choosing review intervals

DocumentReview interval
Quality manual, policy12 months (with management review)
Procedures24 months or on process change
Work instructions24 months, or on equipment/method change
External standards and customer specs12 months currency check, or on customer notification
FormsWith their parent procedure
More in Quality Management & ISO 9001

8d-problem-solving-report-writer

Write and review 8D problem-solving reports for customer complaints and serious nonconformities (automotive and aerospace practice: Ford Global 8D, VDA, GM, Stellantis formats): D0 emergency response, D1 cross-functional team and champion, D2 problem description with 5W2H and is / is-not and no cause in the statement, D3 interim containment within 24 hours with verification and clean point, D4 verified occurrence and escape (non-detection) root causes plus systemic cause, D5 permanent corrective actions for each cause verified before implementation, D6 implementation, validation with production data and removal of containment, D7 PFMEA, control plan and read-across to similar products, D8 closure and recognition. Checks an 8D discipline by discipline for missing content, human-error root causes, missing escape cause or action, late containment and dates out of order.

acceptance-sampling-plan-selector

Select and evaluate acceptance sampling plans for incoming, in-process and final inspection: ANSI/ASQ Z1.4 / ISO 2859-1 single sampling under normal inspection (code letter from lot size and inspection level I, II, III, S-1 to S-4; sample size, Ac and Re from AQL, following the table's arrows to the correct plan; 100% when n reaches the lot size; AQLs above 10 per 100 units), operating characteristic curves (Pa at any quality, producer's quality level, indifference point, LTPD, AOQ and AOQL, binomial or hypergeometric), plans designed from producer and consumer risk, and c = 0 zero-acceptance plans. Covers AQL choice by defect class, switching rules between normal, tightened and reduced inspection, when sampling is not appropriate, and random sampling.

approved-supplier-list-manager

Manage and audit an approved supplier list (ASL) / external provider register for ISO 9001 8.4.1, IATF 16949 8.4 and AS9100 8.4.1: supplier status (approved, conditional, probation, pending, disqualified), scope of approval by commodity and process, risk class, certification and expiry, re-evaluation intervals by risk, conditions with end dates, single-source contingency, approver and customer-directed sources. Audits the list for expired or expiring certificates, overdue re-evaluations, conditional or probation status past its decision date, high-risk suppliers without the required certification, single-source suppliers without backup and missing approvers, and checks purchase orders for suppliers that are off-list, disqualified or pending, or buying outside the approved scope. Covers ERP blocks, PO requirements, off-list and emergency purchases.

apqp-phase-planner

Plan and track Advanced Product Quality Planning (AIAG APQP 3rd edition, IATF 16949) for a new or changed automotive part: back-schedule the five phases (plan and define, product design, process design, product and process validation, launch and feedback) from the start-of-production date by program complexity, with overlap, PPAP lead and safe-launch period; list the deliverables and gate for each phase (DFMEA, DVP&R, feasibility, process flow, PFMEA, control plans, MSA, Ppk, run at rate, PPAP, safe launch, lessons learned); adjust for build-to-print suppliers; flag compressed timelines and late or untracked deliverables against a status list. Covers gate reviews, red/yellow/green status reporting, run at rate and safe-launch exit criteria.

as9100-gap-analyzer

Run an AS9100D / EN 9100:2018 gap analysis for aviation, space and defence suppliers on the requirements added to ISO 9001: on-time delivery and conformity focus, management representative, ethics and human-factors awareness, operational planning and operational risk management, configuration management, product safety, counterfeit-part prevention, special requirements, critical items and key characteristics, external provider register and flow-down, FOD prevention, tooling and NC program control, special process validation, first article inspection (AS9102), traceability, in-service data and nonconforming product control. Generates and scores a worksheet, grades missing core controls as major, and checks invalid n/a claims. Covers AS9101/AS9104, OASIS, AS9102 FAI forms, counterfeit standards (AS5553, AS6174, AS6081), NADCAP and the planned IA9100 transition.

audit-report-writer

Write internal, supplier and pre-certification audit reports with the content ISO 19011:2018 6.5 expects: audit objectives, scope, criteria with revisions, dates, team and auditees, method and sampling statement, specific strengths, findings table and three-part finding details (requirement, evidence, statement), conclusion on the degree of fulfilment of criteria, diverging opinions, follow-up deadlines and distribution. Builds a Markdown report from a JSON audit record, generates the conclusion from the findings (major / minor / none) and flags reports missing required content or findings without clause or evidence. Covers conclusion wording, closing meetings, response expectations and verifying corrective actions.